Bruno Postle 27062a210c Formalise porch lobby: IfcSpace, names, EPset_Pattern, schedule, BoQ (Pattern 130)
- Add entrance-lobby/0 IfcSpace (aggregated into storey 0) with
  Pset_SpaceCommon, Pset_SpaceOccupancyRequirements (OccupancyType=lobby),
  and EPset_Pattern (Pattern 130 Entrance Room / Pattern 150 / Pattern 190)
- Name porch walls: porch south/east/north wall
- Name porch doors: lobby entrance door, lobby interior door
- Add EPset_Pattern (Pattern 130) to both lobby doors
- Schedule: Erect Porch Walls (P2.2, Mar 23-24) under Structure;
  Install Lobby Doors (P4.3, Mar 25) under Openings;
  assign walls 5022/5047/5072 and doors 4972/5234 to tasks
- BoQ: add Lobby Doors (F.2, £750) under Doors section;
  add porch walls to Exterior Walls parametric quantity link;
  update Walls section total to £6950, Doors section to £2250