Bruno Postle 61e64e05d7 Fix schedule: ground floor walls built before first floor walls
The 'Ground Floor' phase (storey 0, ground level) must precede the
'Structure' phase (storey 1, first floor) — lower storeys before upper.

Corrected chain: Foundations → Ground Floor → Structure → Roof → Openings → Finishes

Ground Floor: Mar 12–Apr 1 (walls Mar 12–18, slab Mar 19–25, windows Mar 26–Apr 1)
Structure (first floor walls): Apr 2–17
Roof: Apr 20–24
Openings: Apr 27–29
Finishes (F&F + landscaping): Apr 30–May 5