Bruno Postle bf367bb457 Fix construction schedule sequence ordering
Foundations → Structure → Ground Floor (upper storey) → Roof → Openings → Finishes

- Remove wrong sequence: Ground Floor → Foundations (was backwards, causing upper storey to start Feb 23 before foundations)
- Remove Structure → Roof, Structure → Openings, Roof → Finishes
- Add correct chain: Structure → Ground Floor → Roof → Openings → Finishes
- Cascade dates forward: upper storey Mar 30–Apr 17, roof Apr 20–24, openings Apr 27–29, finishes Apr 30–May 5
- Extend Structure summary to P14D and Finishes summary to P4D to match subtask spans

Closes #28

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
2026-03-20 19:33:26 +00:00